128 - Outfitting has commenced

13.06.14: Outfitting has commenced on Yard no. 128.

Insulation works and laying of floor has commenced in the superstructure.

Block 4, the forward bow section has been placed on the slipway. Installation of equiptment and bow thrusters has also commenced earlier this week.

Block 3 has been taken into the covered painting shed to be sandblasted and later covered with a layer of priming.

Block 2, block 1 and block 6 are also in line awaiting the same threatment.

 

 
This newbuilding will be the first ever to be launched with the bow first at Simek.

 

Yard no. 128 will be delivered to Fletcher Shipping Ltd. in November 2014 with a sister ship following in April 2015.

 

--

09.05.14: Utrustning har startet på bygg nr. 128.

Arbeid med å isolere vegger, tak og gulv samt legging av golv har startet i overbygget.

Blokk 4, den fremste baugseksjonen ble plassert på beddingen tidligere denne uken og installasjon av utstyr og baugpropeller har startet.

Blokk 3 har blitt tatt inn i malerhallen for å bli sandblåst og senere dekket med et lag grunning.

Blokk 2, blokk 1 og blokk 6 venter på den samme behandlingen.


Dette nybygget vil bli det første noensinne som sjøsettes med baugen først ved Simek.

Bygg nr. 128 skal leveres i november 2014 til Fletcher Shipping Ltd. Et søsterskip skal leveres i april 2015.

 

Teknisk Informasjon bygg nr. 128 - Technical Information Yard no. 128